Paraparaumu wastewater treatment plant consenting
We’re working through a process of improvements and consenting issues for the Paraparaumu Wastewater Treatment Plant to ensure it can meet changing public health and environmental standards and community expectations for the next 15 years.
Waikanae, Paraparaumu and Raumati are served by a single wastewater treatment plant, located in Fytfield Place, Paraparaumu. The plant was commissioned in 1981 and upgraded in 2001/02. At the same time, the oxidation ponds (now Pharazyn Reserve) in Waikanae were closed, and all Waikanae wastewater is now pumped to Paraparaumu for treatment.
The Paraparaumu Wastewater Treatment Plant uses biological nutrient removal, one of the most advanced treatment processes in New Zealand. It treats approximately 10-to-12 million litres of wastewater daily to a high standard to protect human and environmental health.
Treated wastewater is discharged to the Mazengarb Drain, which drains to the Lindale/Mazengarb Stream and then to the Waikanae Estuary. During times of low rainfall treated wastewater makes up most of the downstream flow.
Find out about the Paraparaumu Wastewater Treatment Plant.
Background
The objectives of the project are to:
- Upgrade and optimise the performance of the Paraparaumu wastewater treatment plant.
- Work with our iwi partners and stakeholders to identify and implement environmental improvement options. Council is working in partnership with Ātiawa ki Whakarongotai, to investigate and pursue the best environmental and cultural outcomes for the continuous improvement of wastewater treatment and disposal at the Paraparaumu Wastewater Treatment Plant (including, but not limited to, the discharge of treated effluent to land).
- Apply for resource consent enabling the continued operation of the wastewater treatment plant.
The Paraparaumu wastewater treatment plant has five existing consents authorising the discharges of:
- treated wastewater to the Mazengarb Drain
- contaminants to air from treatment plant facilities, associated with odour and operating a boiler
- screened wastewater to land from the base of the storage basin; in March 2024 the storage basin was expanded and lined with an impervious lining. The discharge of treated wastewater makes up a high proportion of the Mazengarb Stream’s flow, especially during dry summer month.
Process
Phase 1 – Upgrades and optimisation
Council implemented a significant improvement plan for the wastewater plant. Upgrades and optimisation activities include:
- a new aeration system to meet the requirement of maintaining dissolved oxygen in the treatment system
- lining and expanding the storage basin to cease discharges to land and provide more storage capacity for community growth and extreme weather events
- improving treatment capability within the treatment plant to improve discharge quality through reduced nutrient and bacteria concentrations
- ongoing rehabilitation of historical contaminated land on the treatment plant site
- planning for riparian planting along the Mazengarb Stream.
Phase 2 – Renewing resource consents
In December 2021, Council lodged an application with Greater Wellington (GW) to renew the resource consents held for the plant. GW agreed Council can continue to operate the plant until a decision is made on the application. GW has engaged a few technical specialists to review our consent application.
Council is seeking consent to continue to operate the existing plant with planned improvements over the next 15 years. Consent has been sought to discharge:
- treated wastewater to the Mazengarb Drain
- contaminants to air from treatment plant facilities
- screened wastewater during extreme wet weather when plant storage capacity is exceeded.
Lining and expansion of the storage basin has been completed, this means that discharges to land have now ceased, and no resource consent is required. While no future discharges of screened wastewater to the Mazengarb Stream are anticipated, resource consent is being sought to provide for any reasonably unanticipated weather events.
Council’s resource consent application has now been notified by Greater Wellington (GW). Submissions on the application must be received by 5pm on Thursday 7 November 2024.
Visit Paraparaumu Wastewater Treatment Plant on GW's consultation platform to find application documents and to make a submission.
Community engagement
We have been working with our iwi partners and key stakeholders throughout the process. If you would like to know more about the treatment plant or the resource consent process, contact us.